Search Our Site

 

 

Helpful Tips - New Construction Rules & Regulations
202.3 Underground Temporary Secondary Service


Temporary underground service will be provided only when the source of power for the temporary service will originate from previously installed underground electric distribution facilities. A temporary service provides electric service for less than a 24-month continuous period where the facilities installed for this service will not be needed to serve other permanent accounts in the near future. Upon application for electric service, the Cooperative will extend up to five feet of temporary underground 120/240-volt service. The owner, member, or developer is responsible for ensuring that a temporary service pole is within five feet of an existing pad-mounted transformer or secondary hand hole suitable for providing such service. The temporary service will be provided under standard applicable rates and connect fees.

In the event the owner, member, or developer requests an underground temporary service extension greater than five feet in length, the requesting party shall pay a CIAC equal to the total estimated cost, including labor and material, of the underground extension plus the temporary service connect fee listed on the Schedule of Charges. This fee is in addition to any other charges required by the SRR .

RETURN TO NEW CONSTRUCTION RULES & REGS

RETURN TO MAIN PAGE

[About Us] [Communications] [Community Involvement]
 [Customer Service/Online Services] [Economic Development] 
[Energy Conservation] [FAQs] [Helpful Tips] [Links]
 [Products & Services] [Privacy Policy] [Touchstone Energy}

Carteret-Craven Electric Cooperative * P.O. Box 1490 * Newport, NC 28570

Office Locations: 1300 Highway 24, Newport, NC; 450 McCotter Blvd., Havelock, NC & 849 Island Road, Harkers Island, NC