Helpful Tips - New Construction Rules & Regulations
202.3 Underground Temporary Secondary Service |
Temporary underground service will be provided only when the source of
power for the temporary service will originate from previously installed
underground electric distribution facilities. A temporary service
provides electric service for less than a 24-month continuous period
where the facilities installed for this service will not be needed to
serve other permanent accounts in the near future. Upon application for
electric service, the Cooperative will extend up to five feet of
temporary underground 120/240-volt service. The owner, member, or
developer is responsible for ensuring that a temporary service pole is
within five feet of an existing pad-mounted transformer or secondary
hand hole suitable for providing such service. The temporary service
will be provided under standard applicable rates and connect fees.
In the event the
owner, member, or developer requests an underground temporary service
extension greater than five feet in length, the requesting party shall
pay a CIAC equal to the total estimated cost, including labor and
material, of the underground extension plus the temporary service
connect fee listed on the Schedule of Charges. This fee is in addition
to any other charges required by the