201.2 Permanent Residential, Commercial & Industrial Buildings

Permanent Residential, Commercial, and Industrial Buildings  

1.      Primary Extensions: When necessary, the Cooperative will furnish and install single phase or multiphase overhead primary distribution facilities to provide service where the distance is too great for secondary service. The owner, member, or developer shall pay a CIAC for the overhead primary distribution line extension at the per foot charge listed on the Schedule of Charges.

2.      Secondary Extensions: The Cooperative will furnish and install a single phase or multiphase overhead secondary service to the normal point of delivery after satisfactory arrangements have been made to pay the CIAC as listed on the Schedule of Charges. The normal point of delivery for overhead service will be on the outside wall of the end of the building nearest to the source of the Cooperative’s facilities entering the member’s premises or at a location designated by the Cooperative.

                     The Cooperative will provide secondary service to a location other than the normal point of delivery. The costs for additional poles and excess per-foot conductor charges are included on the Schedule of Charges. These charges are in addition to any other charges required by the SRR.

RETURN TO NEW CONSTRUCTION RULES & REGS

RETURN TO MAIN PAGE

[About Us] [Communications] [Community Involvement]
 [Customer Service/Online Services] [Economic Development] 
[Energy Conservation] [FAQs] [Helpful Tips] [Links]
 [Products & Services] [Privacy Policy] [Touchstone Energy}

Carteret-Craven Electric Cooperative * P.O. Box 1490 * Newport, NC 28570

Office Locations: 1300 Highway 24, Newport, NC; 450 McCotter Blvd., Havelock, NC & 849 Island Road, Harkers Island, NC
 252-247-3107 * 1-800-682-2217 * customerservice@ccemc.com