1.
Backbone System: Where single phase or multiphase
underground backbone distribution extensions are requested through
planned subdivisions, the owner or developer shall pay a CIAC for each
lot served and per foot of cable as listed on the Schedule of Charges.
Satisfactory arrangements must be made for the payment of these charges
before construction begins. This
charge is in addition to any other charges required by the
SRR
.
2. Undeveloped Areas: When the owner or developer
requests underground primary distribution systems that necessitate the
installation of underground cables through, by, or across areas that
have not been subdivided into lots and offered for sale, the Cooperative
may charge, in advance, a per foot charge for the distance required.
Such charge is specified in the Schedule of Charges. This charge is in
addition to any other charges required by the