Helpful Tips - New Construction Rules & Regulations
201.1 New Overhead Developments |
New Overhead
Developments
1.
Backbone System: Where single phase or multiphase overhead
backbone distribution primary and secondary extensions are requested
through planned subdivisions, the owner or developer shall pay a CIAC
for each lot served and per foot of cable as listed on the Schedule of
Charges. Satisfactory arrangements must be made for the payment of these
charges before construction begins. This charge is in addition to any
other charges required by the Service Rules and Regulations (
SRR
).
2.
Undeveloped Areas: When the owner or developer requests
overhead primary distribution systems that necessitate the installation
of underground cables through, by, or across areas that have not been
subdivided into lots and offered for sale, the Cooperative may charge,
in advance, a per foot charge for the distance required. Such charge is
specified in the Schedule of Charges. This charge is in addition to any
other charges required by the
SRR
.
3.
Conduit Installation: Where the owner or developer of a
subdivision with overhead primary facilities elects to have underground
services under a road and the underground line extensions will be
installed subsequent to paving, the Cooperative will provide the conduit
at the per foot cost listed on the Schedule of Charges.
The
owner or developer shall, at his or her own expense, install the conduit
to meet the specifications provided by the Cooperative. The Cooperative
will provide a layout showing where the conduit must be installed. In
the event the owner or developer requests the Cooperative to install the
conduit prior to the installation of the underground service, the
requesting party shall pay a CIAC equal to the total estimated cost of
the conduit installation. In all cases, the owner or developer will be
responsible for tamping the trench to adequate compaction prior to
paving. In the event that conduit is not installed prior to paving, the
owner, member, or developer will be required to pay all costs incurred
in boring under or cutting through and replacing pavement within the
development or project. The costs for boring are included in the
Schedule of Charges. These charges are in addition to any other charges
required by the
SRR
.
RETURN TO NEW CONSTRUCTION RULES & REGS
RETURN TO MAIN PAGE
|