LINE
EXTENSION POLICIES
The
following Service Rules and Regulations (
SRR
) shall apply to requests for line
extensions, facility relocations, and overhead to underground
conversions under typical construction conditions. Every effort has been
made to cover the vast majority of requests that may be received by the
Cooperative relating to these issues. However, on occasion, situations
may arise that are outside the realm of these policies; such as where in
the sole opinion of the Cooperative construction design and installation
of facilities may be considered non-typical or where a reasonable return
on investment is not anticipated. The Cooperative will consider such
requests, and, if in the opinion of the Cooperative the request will not
cause the Cooperative future problems, the request shall be granted
after satisfactory arrangements have been made for payment of a
contribution in aid of construction (CIAC).
Note:
Line extension cost quotations will be valid for no longer than 90 days.
Generally,
CIAC charges for requests that are outside the realm of these policies
will be calculated based on an engineering estimate. The Cooperative, at
its discretion, may collect a deposit in advance to pay for the costs of
performing engineering estimates for proposed construction or facility
relocation. If a deposit is required to perform an engineering estimate,
the deposit will be applied toward the CIAC if the requested
construction or facility relocation proceeds. Otherwise, the engineering
estimate deposit will be forfeited by the requesting party to offset the
expenses incurred in performing the engineering estimate.
CIAC
charges will be calculated to the highest possible degree of accuracy
using all known facts to compute the estimate. Once the estimate is
complete, the Cooperative will proceed with the requested construction.
The Cooperative normally requires a CIAC and/or other charges to be paid
in advance.
During
the construction of a job or project for which an estimated advance
payment was paid, the Cooperative will accumulate actual costs. The
Cooperative will bill or refund, as appropriate, the difference between
the estimated and actual costs after the total cost of the project has
been determined.
The
Cooperative will review the
SRR
as needed to keep abreast of current
economic and market conditions. The policies, practices, and Schedule of
Charges contained herein are subject to change without notice.