Carteret Craven Electric Cooperative

LINE EXTENSION POLICIES

Table of Contents

 

201.    OVERHEAD EXTENSION POLICY

 

201.1  NEW OVERHEAD DEVELOPMENTS

 

201.2  PERMANENT RESIDENTIAL, COMMERCIAL AND INDUSTRIAL BUILDINGS  

 

201.3 OVERHEAD TEMPORARY SERVICE

 

201.4  OVERHEAD FACILITY RELOCATION

 

201.5  STRUCTURES AND EQUIPMENT MOVING

 

202.    UNDERGROUND EXTENSION POLICY

 

202.1  NEW UNDERGROUND DEVELOPMENTS  

 

202.2  PERMANENT RESIDENTIAL, COMMERCIAL AND INDUSTRIAL BUILDINGS

 

202.3  UNDERGROUND TEMPORARY SECONDARY SERVICE  

 

202.4  OVERHEAD TO UNDERGROUND CONVERSION

 

202.5  UNDERGROUND RELOCATION

 

800.    SCHEDULE OF CHARGES

 

 

 

 

 

 

 

 

Carteret Craven Electric Cooperative

LINE EXTENSION POLICIES

The following Service Rules and Regulations (SRR) shall apply to requests for line extensions, facility relocations, and overhead to underground conversions under typical construction conditions. Every effort has been made to cover the vast majority of requests that may be received by the Cooperative relating to these issues. However, on occasion, situations may arise that are outside the realm of these policies; such as where in the sole opinion of the Cooperative construction design and installation of facilities may be considered non-typical or where a reasonable return on investment is not anticipated. The Cooperative will consider such requests, and, if in the opinion of the Cooperative the request will not cause the Cooperative future problems, the request shall be granted after satisfactory arrangements have been made for payment of a contribution in aid of construction (CIAC).

Note: Line extension cost quotations will be valid for no longer than 90 days.

Generally, CIAC charges for requests that are outside the realm of these policies will be calculated based on an engineering estimate. The Cooperative, at its discretion, may collect a deposit in advance to pay for the costs of performing engineering estimates for proposed construction or facility relocation. If a deposit is required to perform an engineering estimate, the deposit will be applied toward the CIAC if the requested construction or facility relocation proceeds. Otherwise, the engineering estimate deposit will be forfeited by the requesting party to offset the expenses incurred in performing the engineering estimate.  

CIAC charges will be calculated to the highest possible degree of accuracy using all known facts to compute the estimate. Once the estimate is complete, the Cooperative will proceed with the requested construction. The Cooperative normally requires a CIAC and/or other charges to be paid in advance.

During the construction of a job or project for which an estimated advance payment was paid, the Cooperative will accumulate actual costs. The Cooperative will bill or refund, as appropriate, the difference between the estimated and actual costs after the total cost of the project has been determined.

The Cooperative will review the SRR as needed to keep abreast of current economic and market conditions. The policies, practices, and Schedule of Charges contained herein are subject to change without notice.

201.    OVERHEAD EXTENSION POLICY

Upon application for electric service, the Cooperative will furnish and install overhead primary and secondary service within its service area, or where allowed by law, to new developments, to permanent residential dwellings, and to commercial, industrial, or public buildings.

 

Prior to the installation of the Cooperative’s electric facilities, the owner, member, or developer will furnish, without cost to the Cooperative, necessary easements and rights-of-way and will be required to initially cut and clear the same as specified by the Cooperative. If requested by the owner, member, or developer, the Cooperative will clear the rights-of-way of vegetation if the requesting party pays in advance all estimated costs including labor, equipment fees, and materials associated with the clearing. The owner, member, or developer will have lot lines established and staked, the right of way cleared of vegetation and other obstructions, and the project prepared to final grade before construction of the permanent electrical system begins.

The type of construction and location of said facilities will be at the option of the Cooperative. Should the requesting party desire changes in either location or type of construction, and if the Cooperative agrees to the requested changes, such installations will be made only upon the owner, member, or developer consenting to pay the Cooperative any estimated additional costs incurred in advance.

The Cooperative will construct its facilities to meet or exceed existing minimum standards of the latest edition of the National Electrical Safety Code, the Rural Utility Service’s Construction Specification Manuals, and any other applicable codes or standards that exist at time of construction. The facilities will be designed using sound engineering principles and practices. Facilities will also be operated in accordance with sound engineering principles and practices.

Facilities will be extended after the Cooperative is in possession of any required rights-of-way easements and satisfactory arrangements have been made for payment of any applicable CIAC. All agreements for these services shall be reduced to writing and will be provided under the following additional terms and conditions:

201.1  NEW OVERHEAD DEVELOPMENTS

1.      Backbone System: Where single phase or multiphase overhead backbone distribution primary and secondary extensions are requested through planned subdivisions, the owner or developer shall pay a CIAC for each lot served and per foot of cable as listed on the Schedule of Charges. Satisfactory arrangements must be made for the payment of these charges before construction begins. This charge is in addition to any other charges required by the Service Rules and Regulations (SRR).

2.      Undeveloped Areas: When the owner or developer requests overhead primary distribution systems that necessitate the installation of underground cables through, by, or across areas that have not been subdivided into lots and offered for sale, the Cooperative may charge, in advance, a per foot charge for the distance required. Such charge is specified in the Schedule of Charges. This charge is in addition to any other charges required by the SRR.

 

 

3.      Conduit Installation: Where the owner or developer of a subdivision with overhead primary facilities elects to have underground services under a road and the underground line extensions will be installed subsequent to paving, the Cooperative will provide the conduit at the per foot cost listed on the Schedule of Charges.

The owner or developer shall, at his or her own expense, install the conduit to meet the specifications provided by the Cooperative. The Cooperative will provide a layout showing where the conduit must be installed. In the event the owner or developer requests the Cooperative to install the conduit prior to the installation of the underground service, the requesting party shall pay a CIAC equal to the total estimated cost of the conduit installation. In all cases, the owner or developer will be responsible for tamping the trench to adequate compaction prior to paving. In the event that conduit is not installed prior to paving, the owner, member, or developer will be required to pay all costs incurred in boring under or cutting through and replacing pavement within the development or project. The costs for boring are included in the Schedule of Charges. These charges are in addition to any other charges required by the SRR.

201.2  PERMANENT RESIDENTIAL, COMMERCIAL AND INDUSTRIAL BUILDINGS 

1.      Primary Extensions: When necessary, the Cooperative will furnish and install single phase or multiphase overhead primary distribution facilities to provide service where the distance is too great for secondary service. The owner, member, or developer shall pay a CIAC for the overhead primary distribution line extension at the per foot charge listed on the Schedule of Charges.

2.      Secondary Extensions: The Cooperative will furnish and install a single phase or multiphase overhead secondary service to the normal point of delivery after satisfactory arrangements have been made to pay the CIAC as listed on the Schedule of Charges. The normal point of delivery for overhead service will be on the outside wall of the end of the building nearest to the source of the Cooperative’s facilities entering the member’s premises or at a location designated by the Cooperative.

                     The Cooperative will provide secondary service to a location other than the normal point of delivery. The costs for additional poles and excess per-foot conductor charges are included on the Schedule of Charges. These charges are in addition to any other charges required by the SRR.

 

 

 

 

 

 201.3 OVERHEAD TEMPORARY SERVICE

Upon application for electric service, the Cooperative will extend temporary overhead distribution facilities. A temporary service supplies electricity for less than a 24-month continuous period, where the facilities installed for this service will not be needed to serve other accounts in the near future. A Temporary Service Connect Fee will be charged in accordance with the Schedule of Charges. This charge is in addition to any other charges required by the SRR. Temporary services will be furnished and installed under the following terms and conditions:

1.      Temporary Secondary Service Extensions – Up to 75 Feet in Length: The Cooperative will extend up to 75 feet of temporary overhead 120/240 volt triplex service for construction of buildings, homes, or other structures. The temporary service will be provided under standard applicable rates and temporary service-connect fees. The member is responsible for ensuring that their temporary service pole is sufficiently braced and of sufficient height to meet the clearance requirements of the National Electric Safety Code, and other applicable state and local codes. The party requesting temporary service is responsible for clearing the rights-of-way of vegetation and other obstacles.

         Where the Cooperative must install an additional pole or poles to provide a temporary service that is equal to or less than 75 feet in length, the owner, member, or developer must pay a CIAC based on the total estimated cost of setting the pole(s) added to the estimated cost of retiring the pole(s) less any salvageable materials. These charges are in addition to any other charges required by the SRR.

2.      Temporary Primary and/or Secondary Service Extensions – Greater than 75 Feet in Length: The Cooperative will extend and furnish temporary overhead primary and secondary electric lines in excess of 75 feet to buildings, construction projects, asphalt plants, carnivals, fairs, temporary facilities, or other non-permanent installations. A CIAC will be based on the total estimated line extension cost added to the estimated cost of retiring the facilities less any salvageable materials.

201.4  OVERHEAD FACILITY RELOCATION

The Cooperative, upon the request of a property owner, member, or developer, will consider relocating existing overhead facilities. Any relocation of facilities will be analyzed with a view to better the Cooperative’s system and to not cause the Cooperative future problems. Betterment of the electric system occurs when, in the sole judgment of the Cooperative, the proposed change results in needed repair or improvement that provides easier maintenance, repairs, replacement, or reconstruction of the facility, and, in the sole judgment of the Cooperative, the economic return of the project justifies the investment in the facility relocation. The owner, member, or developer making the request for relocation will be responsible for all costs incurred that do not result in betterment of the electric system, for obtaining all necessary rights-of-way, and for all costs associated with cutting and clearing the rights-of-way of vegetation or other obstructions. If the Cooperative agrees to the relocation as requested, the party requesting the relocation will make arrangements for payment of the total estimated non-betterment costs before the relocation begins.

201.5  STRUCTURES AND EQUIPMENT MOVING

                     The Cooperative, where practicable and upon request, will raise or lower lines to afford safe passage for structures or equipment being moved. Parties making such requests will be required to pay the total costs of the work performed. The parties will be required to make an advance deposit of the total estimated costs. The Cooperative will perform a final accounting of the costs, and either bill or refund the difference between the actual and estimated costs.

202.    UNDERGROUND EXTENSION POLICY

Upon application for electric service, the Cooperative will furnish and install underground primary and secondary service within its service area, or where allowed by law, to new developments, permanent residential dwellings, and to commercial, industrial, or public buildings.

Prior to the installation of the Cooperative’s electric facilities, the owner, member, or developer will furnish, without cost to the Cooperative, necessary easements and rights-of-way and will be required to initially cut and clear the same. Lot lines must be established and staked, the right-of-way cleared of vegetation and other obstructions, and the project prepared to final grade before construction begins. The owner, member, or developer is responsible for identifying, locating, and exposing all privately-owned below ground facilities and obstructions prior to the installation of the underground electric facilities. The Cooperative will not be responsible for damage to any privately-owned underground facilities that are not identified, located, and exposed prior to the installation of the underground electric lines.

Where, due to conditions in the soil, as much as 5 percent of the trenching work cannot be accomplished by the use of standard trenching machines and techniques, excess costs incurred by such conditions may be charged by the Cooperative. The excess charge for abnormal trenching is specified in the Schedule of Charges. Where there are other unusual conditions, such as high water or unusual local wiring or electrical code requirements which require installation procedures and materials not normally used, the excess cost of such procedure may be charged by the Cooperative. These charges are in addition to any other charges required by the SRR.

 

 

 

Additional charges may be made by the Cooperative to defray the expense of constructing temporary overhead facilities installed at the request of and to accommodate the owner or developer through, by, or into areas that will ultimately be served by underground facilities. The CIAC will be based on the total estimated line extension cost, plus the estimated cost of retiring the facilities, less any salvageable materials. These charges are in addition to any other charges required by the SRR.

The type of construction and location of facilities will be at the option of the Cooperative. Should the owner or developer desire changes in either location or type of construction, and provided that the Cooperative agrees that the requested changes will not present future problems, such installations will be made only upon the owner or developer agreeing to pay to the Cooperative the estimated additional cost incurred. These charges are in addition to any other charges required by the SRR.

The Cooperative will construct its facilities to meet or exceed the then existing minimum standards of the latest edition of the National Electrical Safety Code, the Rural Utility Service’s Construction Specification Manuals, and any other then existing applicable codes or standards that exist at the time of construction. The facilities will be designed and operated using sound engineering principles and practices.

Where the owner, member, or developer wishes to pave roads, driveways, or other areas prior to the installation of the underground distribution facilities, the Cooperative will provide conduit and a layout showing where the conduit must be installed. The owner or developer, at his or her own expense, will be required to install the conduit under roads or other paved areas to meet the specifications provided by the Cooperative. In the event that the owner or developer requests the Cooperative to install the conduit prior to the installation of the underground service, the requesting party shall pay a CIAC equal to the total estimated cost of the conduit installation. In all cases, the owner or developer will be responsible for tamping the trench to adequate compaction prior to paving. In the event that conduit is not installed prior to paving, the owner, member, or developer will be required to pay all costs incurred in boring under or cutting through and replacing pavement within the development or project. The costs for boring are included in the Schedule of Charges. These charges are in addition to any other charges required by the SRR.

Protection of shrubs, trees, and grass sod during the installation of the underground facilities will be the responsibility of the owner or developer.

The owner or developer will hold the Cooperative and/or its subcontractors harmless from all costs and claims for damages or injury (including death) and including reasonable attorney’s fees. It will be the responsibility of the owner or developer to re-seed and/or maintain the trench cover.

 

The owner or developer will be required to pay all required deposits and costs incurred in boring under or cutting through and replacing pavement within the development. The costs for boring are included in the Schedule of Charges. This charge is in addition to any other charges required by the SRR.

All agreements for these services shall be reduced to writing and will be provided under the following additional terms and conditions.

202.1  NEW UNDERGROUND DEVELOPMENTS 

1.   Backbone System: Where single phase or multiphase underground backbone distribution extensions are requested through planned subdivisions, the owner or developer shall pay a CIAC for each lot served and per foot of cable as listed on the Schedule of Charges. Satisfactory arrangements must be made for the payment of these charges before construction begins.  This charge is in addition to any other charges required by the SRR.

2.   Undeveloped Areas: When the owner or developer requests underground primary distribution systems that necessitate the installation of underground cables through, by, or across areas that have not been subdivided into lots and offered for sale, the Cooperative may charge, in advance, a per foot charge for the distance required. Such charge is specified in the Schedule of Charges. This charge is in addition to any other charges required by the SRR.

202.2  PERMANENT RESIDENTIAL, COMMERCIAL AND INDUSTRIAL BUILDINGS

1.   Primary Extensions: When necessary, the Cooperative will extend underground primary distribution facilities to provide service where the distance is too great for secondary service. A CIAC is required for underground primary extensions. The underground primary extension charge per foot is listed on the Schedule of Charges. This charge is in addition to any other charges required by the SRR.

2.   Secondary Extensions: The Cooperative will furnish and install a single phase or multiphase underground secondary service after satisfactory arrangements have been made to pay the CIAC listed on the Schedule of Charges. These charges are in addition to any other charges required by the SRR.

202.3  UNDERGROUND TEMPORARY SECONDARY SERVICE 

Temporary underground service will be provided only when the source of power for the temporary service will originate from previously installed underground electric distribution facilities. A temporary service provides electric service for less than a 24-month continuous period where the facilities installed for this service will not be needed to serve other permanent accounts in the near future. Upon application for electric service, the Cooperative will extend up to five feet of temporary underground 120/240-volt service. The owner, member, or developer is responsible for ensuring that a temporary service pole is within five feet of an existing pad-mounted transformer or secondary hand hole suitable for providing such service. The temporary service will be provided under standard applicable rates and connect fees.

In the event the owner, member, or developer requests an underground temporary service extension greater than five feet in length, the requesting party shall pay a CIAC equal to the total estimated cost, including labor and material, of the underground extension plus the temporary service connect fee listed on the Schedule of Charges. This fee is in addition to any other charges required by the SRR.

202.4  OVERHEAD TO UNDERGROUND CONVERSION

1.   OH to UG Residential Secondary Services

a.   When the owner, member, or developer requests that an overhead secondary service previously installed for a permanent residence be removed and replaced with a new secondary underground service, and when there has been no increase in the member’s service requirements that necessitate an upgrade to the existing overhead service conductors, the requesting party will pay to remove the existing overhead service. The underground service will be installed in accordance with the applicable sections of the Underground Extension Policy. This charge is in addition to any other charges required by the SRR.

b.   When it becomes necessary for the Cooperative to change overhead service wires because of an increase in the owner’s service requirements, the charge to remove the existing overhead service may be waived, and upon the request of the owner the new service may be installed underground. The underground secondary service will be installed in accordance with the applicable sections of the Underground Extension Policy. This charge is in addition to any other charges required by the SRR.

2.   OH to UG Non-Residential Secondary Services

a.   When the owner, member, or developer requests that an overhead secondary service previously installed to serve a permanent building be removed and replaced with a new secondary underground secondary service, and when there has been no increase in the member’s service requirements that necessitate an upgrade to the existing overhead service conductors, the requesting party will pay to remove the existing overhead service. The underground service will be installed in accordance with the applicable sections of the Underground Extension Policy. This charge is in addition to any other charges required by the SRR.

b.   When it becomes necessary for the Cooperative to change overhead service wires because of an increase in the owner’s service requirements, the charge to remove the existing service may be waived, and upon the request of the owner, the new service may be installed underground. The underground secondary service extension will be governed by the applicable provisions of the Underground Extension Policy.

3.   OH to UG Primary Distribution Lines

            When the owner, member, or developer requests that an existing overhead primary line be replaced with primary underground cable, and provided that the Cooperative agrees that the requested changes will not present future problems, the requesting party will make satisfactory arrangements to pay the total estimated costs of removing the existing facilities, plus the total estimated costs including labor and materials of installing the facilities underground. The value of salvaged materials will be credited to the costs, and the final billing will be adjusted as necessary. This charge is in addition to any other charges required by the SRR.

202.5  UNDERGROUND RELOCATION

1.   UG Secondary Service:  Upon request, the Cooperative may agree to relocate an underground service. Any expenses incurred in relocating an underground electric service due to the owner’s, member’s, or developer’s alteration in their service entrance facilities and/or meter base, or to accommodate any other request for the underground secondary service drop being relocated, shall be borne by the requesting party. The CAIC for underground service relocation are listed on the Schedule of Charges. This charge is in addition to any other charges required by the SRR.

2.   UG Primary: Upon request, the Cooperative may agree to relocate an existing underground primary line. Any expenses incurred in relocating or extending an underground electric primary line due to the owner’s alteration in their service entrance facilities and/or meter base, or to accommodate any other request for the underground primary line being relocated, shall be borne by the requesting party. Relocation will begin once satisfactory arrangements have been made by the owner, member, or developer to pay the total estimated cost of the relocation including labor and materials. This CAIC is in addition to any other charges required by the SRR.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Carteret Craven Electric Cooperative

800.                                                 SCHEDULE OF CHARGES

 

I.       OVERHEAD

            A.        New Developments

                        1. Backbone                                                                                (per lot)        $500.00

                                    a. One Phase System                                                    (per foot)            2.00

                                    b. Multiphase System                                                     (per foot)          3.50

           

                        2.         Extensions through Undeveloped Areas   

                                    a. One Phase System                                                    (per foot)         $4.10

                                    b. Multiphase System                                                     (per foot)           5.60

                       

            B.        Permanent Residential Dwellings

                        1.         Primary Extensions

a. One Phase System Up To 1000 Ft.                                                    $1.00

b. One Phase System Beyond 1000 Ft.                       (per foot)              4.10

c. Multiphase System                                                     (per foot)              5.60

 

                        2.         Secondary Service Extensions

                                    a. All Permanent Overhead Residential Services                    $55.00

                                    b. One Phase beyond Normal POD                             (per foot)              1.00

                                    c. Multiphase beyond Normal POD                              (per foot)              1.50

                                    d. Additional Pole Beyond Normal POD                      (each)              225.00

           

C.        Permanent Commercial, Industrial, or Non-Residential     

                        1.         Primary Extensions

                                    a. One Phase System Up To 1000 Ft.                                                    $1.00

                                    b. One Phase System beyond 1000 Ft.                       (per foot)              4.10

                                    c. Multiphase System Up To 700 Ft.                                                           2.80

                                    d. Multiphase System beyond 700 Ft.                          (per foot)              5.60

                        2.         Secondary Service Extensions

                                    a. All Permanent Overhead Non-Residential Services                        $55.00

                                    b. Single Phase beyond Normal POD                          (per foot)              1.00

                                    c. Multiphase beyond Normal POD                              (per foot)              1.50

                                    d. Additional Pole beyond Normal POD                                               225.00

 

D.        Temporary Service – Residential, Commercial, or Industrial

                        1.         Secondary Service Up to 75 Feet

                                    a. Connect Fee                                                                                         $55.00

                                    b. Additional Pole                                                           (each)               225.00

                        2.         Primary or Secondary Extensions More Than 75 Feet

                                    a.         Connect Fee                                                                                  $55.00

                                    b.         Line Extension and Retirement Charge                                 Total Cost

 

II.      UNDERGROUND

            A.        New Developments – typical construction

                        1.         Backbone System

                                    Cost per lot                                                                                                 $1,000

                                    a. Secondary Cable                                                        (per foot)                2.00

                                    b. Single Phase Primary Cable                                     (per foot)                3.00

                                    c. Multi phase                                                                  (per foot)                9.00

                                   

                        2.         Extensions through Undeveloped Areas   

                                    a. One Phase System                                                    (per foot)             $9.00

                                    b. Multi phase                                                                  (per foot)             12.00

                                   

            B.        Permanent Residential, Commercial, or Industrial Buildings

                        1.         Primary Extensions

                                    a. Single Phase Cable (per foot)                                                                $4.50

                                    b. Multiphase Cable (per foot)                                                                       9.00

 

                        2.         Secondary Extensions

                                    Cost per service drop                                                                               $150.00

                                    a. Single Phase Cable                                                   (per foot)                 3.00

                                    b. Multiphase Cable                                                        (per foot)                 4.00

 

            C.        Temporary Service Connect Fee (5 feet maximum)                                    $55.00

            D.        Abnormal Trenching (per foot)

                        1. Hand trenching                                                                                                   $15.00

                        2. All others                                                                                                      Actual cost

            E.        Boring Under Streets and Driveways                                                    Actual cost

            F.         Underground Service Relocation

                        1.         Up To 15 Feet

                                    a. Underground Splice                                                   (each)                   $5.00

                                    b. Hand Trenching                                                           (per foot)             15.00

                                    c. Additional Cable                                                         (per foot)               4.50

                        2.         More Than 15 Feet                                                                               Total Cost

 

III.     OVERHEAD TO UNDERGROUND CONVERSIONS

            A.        Residential Secondary Service

                        1.         No Load Added

                                    a. Existing Overhead Service Retirement                               $105.00

                                    b. UG Service                                                   (per foot)         $3.00 plus $150

                        2.         Load Added Which Requires an OH Service Conductor Upgrade

                                    a. Existing Overhead Service Retirement                                   $0.00

                                    b. UG Service                                                   (per foot)         $3.00 plus $150

           

B.        Non-Residential Secondary Service

                        1.   No Load Added                                                                              Total Cost

                        2.   Load Added Which Requires an OH Service Conductor Upgrade

                                    a. Existing Overhead Service Retirement                                       $0.00

                                    b. Single Phase Service                                 (per foot)          $3.00 plus   150

                                    c. Multiphase Service                                      (per foot)          $4.00 plus $150

IV.    CONDUIT

1.   Two-Inch PVC                                                        (per foot)                             $1.00

2.   Two and one-half inch PVC                                  (per foot)                               1.50

3.   Four-inch PVC                                                       (per foot)                              2.50

4.   Four-inch steel                                                        (per foot)                             11.00

V.     DEPOSITS

1.      Residential: The greater of $250.00 or the highest estimated power bill for two and one half months of service.

2.   Other than Residential: the greater of $250.00 or the highest estimated power bill for two and one half months of service.

3.   Temporary service for contractors                                                                   $25.00

VI.    SERVICE FEES

1.   Connect                                                                                                              $15.00

2.   Field Service Charge                                                                                       30.00

            Includes:

Delinquent disconnect trip

Delinquent reconnect trip

Delinquent field extension

Delinquent field collection

3.   Delinquent Service Charge                                      the greater of $5.00 or 1.5%

4.  Extension Service Charge                                        the greater of $5.00 or 1.5%

5.  Meter Test                                                                                                          $45.00

6.   Overtime                                                                                                            45.00

7.   Premium Service                                                                                                25.00

8.   Returned Check                                                                                                 25.00

9.   Electronic Returned Item Fee                                                                          10.00

10. Guarantee Contract fee                                                                                     10.00

11. Credit Check fee                                                                                               10.00

12. Trip Cost Recovery                                                                                            30.00

VII.   ERC LOAN FEES

1.   Energy Audit                                                                                                    $100.00

2.   Loan Processing Fee under $ 3,000                                                                10.00

3.   Loan Processing Fee over $ 3,000                                                                  43.001

4.   Closing Fee under $ 3,000                                                                                76.001

5.   Closing Fee over $ 3,000                                                                               142.001

 

 

                1 Board authorized changes to be made as necessary to reflect actual fees.

 

VIII.  ENERGY AUDIT FEES

1.   Member Only Walk-through (no equipment sized)                                  No Charge

2.   Members (with equipment sized)                                                                  $100.00

3.   Members (equipment sized from building plans)                                         150.00

4.   All Non-Member audits                                                                                    250.00

IX.    METER TAMPERING FEES